Projected Task Schedule for the Year 2003


 
02/29/04 Obtain and import CHART II data for Year 2003
 
03/15/04 Developement of a java-based interface for the input of road and segment information
 
04/30/04 Data input for incident reports not in the CHART-II database
 
 
 
04/30/04 Preliminary analysis for CHART performance for Year 2003
 
06/15/04 Data quality analysis and incident distribution statistics for the incident records
 
08/31/04 Analysis of incident characteristics and CHART performance
 
09/30/04 Benefit analysis
 
10/30/04 Secondary Incident analysis
 

Research Group of Dr. Gang-Len Chang,   Department of Civil Engineering, University of Maryland
Steven M. Rochon, Project Manager, Maryland State Highway Administration
Michael Zezeski, CHART Program Director, Maryland State Highway Administration
Thomas Hicks, Director, OOTS, Maryland State Highway Administration